Morning:
Today was the big concrete pour day. The concrete crew from Tom Wood Concrete, Tommy, Willson, and Anthony, finished the footer forms, adding two rows of reenforcing bars between the two boards of the footers
The completed forms:
Looking west along the south side of the house
|
Looking south along the east end of the house
|
Footer form detail showing the bent and positioned rebar
|
Angeles Concrete Cement And Slurry Pumping Trucks On Site Ready Go:
At about 10 AM, Angeles Concrete arrived on scene and set up a large pumping truck. The tall boom was able to reach all areas of the footer. It took two trucks to bring the concrete needed. There was a point when the pumping nozzle became clogged because the second load of concrete was too thick. After getting the nozzle unclogged workers ran the concrete back into the mixing truck adding in more water to get it flowing again, and then switched to a different, more flexible, tube nozzle.
Afternoon:
The whole crew worked in unison with Tommy positioning the nozzle and directing the flow of slurry, Anthony following to scrape away excess concrete, ensure all voids were filled, and remove the horizontal rebar support wires, and Wilson completing the process by smoothing the surface and placing the required vertical rebar pieces.
The following video compresses the entire 4 hour event from start to finish into 9 minutes: